← All projects / PROJECT 041 — DELIVERED 2027

North Quay
Deck

Zürich, Switzerland Transfer deck · 41,000 m² Post-tensioned concrete Client: SBB Infrastructure
North Quay deck elevation
/ 01

The problem

SBB needed 41,000 m² of new deck over four live rail corridors at Zürich North Quay — with no full possessions available. Every night closure was 6.5 hours; there were 312 of them in the programme. A conventional cast-in-place slab would have needed 40-hour pours.

Our answer: a precast, post-tensioned segmental deck in 2.4 m units, each weighing under the crane's night rating, stitched with in-situ joints poured inside the same shift. The rail stayed live, one corridor at a time, for the entire twenty months.

Constraints we designed around

  • Live 25 kV overhead line above the works — 4.1 m clearance, no exceptions
  • Night-only access: crane-up at 22:40, crane-off by 05:10
  • Vibration limits set by the operator's track standards
  • Zero stored materials on the permanent works at shift end
/ 02

Specification

Deck area
41,000 m²
Structural depth
620 mm
Segments
1,842 precast units
Post-tensioning
19 internal + 4 external tendons / unit
Night closures used
312 of 312
Programme saving vs. in-situ
11 months
/ 03

Outcome

The deck opened on 4 September 2027, eleven months ahead of the in-situ baseline. Instrumentation installed during construction now streams strain and temperature data to our Zürich office — the first MERIDIAN project with a live digital twin feeding back into the maintenance manual.

The operator has adopted the segmental night-construction sequence as a standard detail for future deck replacements. We consider that the real deliverable.